Newcastle Central Library

Release Date: 10 October 2007

Project

Newcastle Central Library 

Supplying depot
Newcastle Depot
Address
Cross Carliol Street, Newcastle-upon-Tyne, NE1 8AR
Date Supplied
1/8/2007
Contractor
Tolent Construction
Client if known

Quantity / Materials used

300 tonne Cut & Bent Reinforcing Bar

Specific issues / problems  
Due to the availability of rebar bending schedules, site storage space and site programme an express delivery service was required once schedules were available.  A timed delivery service was essential due to site location being in Newcastle City centre.
Services / products used
Cares approved Cut & Bent Reinforcing Bar